Onsite Updates
August 2021
Front Side External Plaster work completed
Plumbing RCC Shaft on 14th Floor
12th Floor Refuge Area Flooring
July 2021
External Plaster Work
13th Floor Duct Shuttering Work
11th Floor Part 3B Staircase Plaster Work
June 2021
Scafolding Work for External Plaster
External Plaster Preparation
External Plaster Preparation
Internal Block work on 12th FLoor
RCC Rendering Work
Electric Jhari Patti Work
Toilet Waterproofing Work