Onsite Update
Overall Site Progress

August 2020

Rear End View

August 2020

Internal Common Development and External Elevation

August 2020

B Block Foyer Work

August 2020

B Block Polishing Work on 11th Floor

August 2020

B Block Flooring Work

August 2020

Block A Final Cleaning for Possession

July 2020

Block A Final Door Color Work

July 2020

Block C Final Door Frame Polish Work

July 2020

Final Ceiling Work in progress

July 2020

Block B Tiling Work in Progress

July 2020

Block B Tiling Work in Progress

July 2020

Common Plot Development

July 2020

Block A Color & Texture Work Completed

May 2020

Block A, B, C, D Lift Installation in Progress

May 2020

Color Work Completed

March 2020

Common Area Development

February 2020

Common Area Development In Progress

January 2020

Overall Site Progress

December 2019

Color Work In Progress

November 2019

Overall Site Progress

October 2019

Texture Work Completed

October 2019

Flooring Work

August 2019

Color Work

July 2019

Texture Work

July 2019

Ongoing Exterior Treatment

June 2019

Ongoing Exterior Treatment

June 2019

Ongoing Exterior Treatment

June 2019

Ongoing Plaster Work

April 2019

Sun Sky Park

March 2019

Sun Sky Park

February 2019

Site Progress

January 2019

Eighth Floor Block D

January 2019

Primer Coat

December 2018

Block Work

December 2018

Block Work

October 2018

Sixteenth Floor Slab

September 2018

Plasterwork In Progress

September 2018

Plaster Work

August 2018

Block Work

August 2018

Slab Shuttering Work

August 2018

Site Progress

July 2018

Skypark Site Progress

July 2018

Onsite Workers Training

June 2018

Block Work

June 2018

Eleventh Floor Slab

June 2018

Fouth Floor Slab

May 2018

Overall Progress

May 2018

Block Work And Sample Unit Ready

April 2018

Tenth Floor Slab

April 2018

Block Work

April 2018

Blockwork In Progress

March 2018

Overall Site Progress

March 2018

Sixth Floor Slab

February 2018

Overall Site View

January 2018

Fourth Floor Slab

December 2017

First Floor Slab

November 2017

Upper Basement Slab

October 2017

Lower Basement Slab

September 2017

Lower Basement Slab

August 2017

Footings

July 2017

PCC

June 2017

Raft Foundation

June 2017

Excavation

May 2017

 
Project Clearances
KNOW MORE
E-Brochure
To Receive a Brochure

Please fill up the details in the form below, We shall email you the brochure immediately to your registered Email address.

Inquiry
Please Enter Your Name ! Please Enter Valid Name ! Please Enter Your 10 Digits Mobile No. ! Please Enter Valid Mobile No. ! Please Enter Your Email Id ! Please Enter Valid Email Id ! Please enter Convenient Time to Call! Please Enter Any Comment ! Please Fill Up the Captcha !